    Hello,

    With a project team and SH created, I activated the availability on the project, so I can specify my team availability for each team member.
    Now I add some SH on the project, and the availability increases (I saw it on the bundle timeline) ! I took a look at the availability screen and each new SH had a default availability set on all created sprints…

    Thanks for taking care of this.

    [I run an IS R6#14.3 Pro Standalone (build 342).]

    #17949

    Nicolas Noullet
    Superadministrador

    Hello,

    This looks like a bug, thanks for the report we will try to reproduce it.

    In the meantime you can define manually the availabilities to 0 (do it on the first cell then you can expand the value to the next cells as you would do in Excel).

    By the way, we recommend that you upgrade (https://www.icescrum.com/documentation/upgrade-guide/) to the latest version (R6#14.8 : https://www.icescrum.com/blog/version-r614/) to benefit from all the features and bug fixes.