iceScrum | Splitting estimated stories – iceScrum

iceScrum Foros Discutir de iceScrum

Viendo 4 entradas - de la 1 a la 4 (de un total de 4)

  • Autor
    Entradas
  • #259972

    tziem
    Participante

    Hi,
    as a PO I cannot split estimated stories.
    I also cannot change the estimation value.
    The documentation says that Product Owners have the permission of a Scrum Master and Scrum Masters have the permission of a Team Member.

    Best regards
    Thomas

    #260417

    Vincent Barrier
    Superadministrador

    Hello,
    Thank you for your report:
    – There is a bug as a PO you should be able to split the story. We are reproducing the problem.
    – The ability to update the estimation is for the SM / TM only. Can you share where the documentation says something wrong?
    Thank you!

    #260471

    tziem
    Participante

    Hi Vincent,
    here the part of the documentation:

    Roles, teams & projects


    A Team Member can estimate stories. This works fine.
    A Scrum Master has the permissions of the Team Member, plus…
    This means for me that also a Scrum Master can estimate stories. This works also.
    A Product Owner has the permissions of the Scrum Master, plus…
    This means for me that also a Product Owner can estimate stories, because he can do all the things a SM can do.
    Or am I wrong?
    ~Thomas

    #260554

    Vincent Barrier
    Superadministrador

    You are right, something is missing in the documentation. I have updated it.
    Also the bug is fixed in the trunk. https://github.com/icescrum/iceScrum/commit/d27400d1361f8ca3393a518faab93144c5401dde

    Cheers;

Viendo 4 entradas - de la 1 a la 4 (de un total de 4)

El foro ‘Feedback, defects, evolutions’ está cerrado y no se permiten nuevos debates ni respuestas.