    Good afternoon, first of all I am new using Icescrum and maybe the error is basic for you. The problem is the following, I successfully create the stories that go to the sandbox, I accept them as valid user stories in the “accept as history” option, after that I am informed that the story was sent to “Product Backlog “. When by the tab managed to access it I do it without problems, but I can not see it reflected in the table that is created on the left from which I can move to the Sprint. If anyone knows why or wants more detail would be of great help.

    #47812

    Nicolas Noullet
    Keymaster

    Hi,

    In order to be displayed in the left table and to be planned in a sprint, a story needs to be in the “Estimated” state, the state that comes after “Accepted”.

    An “Accepted” from the “Product Backlog” moves to the “Estimated” state when it is estimated by a team member or ScrumMaster (Product Owner(s) cannot estimate a story).

    In order to estimate the effort of a story (usually in story points), a member just has to click on the “?” on the post-it and select a value.