    Hi,

    as far as I remember I can specify whether weekends shall be shown in the burndown or not during project creation.
    However, is it possible to remove (or fading out) weekends from the burndown AFTER project creation?
    At least for the remeining sprints that have not started?

    If there is no UI for that, I don’t mind changing fields in the database directly.

    #10999

    Nicolas Noullet
    Keymaster

    Hi,

    This setting can be changed after the project creation by using the “practices” menu of the project dropdown (on the top left of the window). This menu is accessible for ScrumMasters and the project creator.