    We are using a locally installed version of iceScrum.

    We just started on 2nd sprint and noticed that we cannot « Declare a story as Done » even when all associated tasks are done. We were able to declare as done with the first sprint.

    Has anyone seen this before or have any ideas?

    Thank you,

    Brian

    #10948

    Nicolas Noullet
    Maître des clés

    Hello Brian,

    Here are the two requirements to make the « Declare a as done » menu appear:
    – The story must be in progress
    – The user must be Product Owner

    Are you sure that these requirements are met? If so, the menu should be displayed. If it is, does it work?

    #10949

    Kagilum
    Maître des clés

    Hi Nicolas,

    Thank you for the response. You are right; the stories in this sprint are all in a state of “Planned”. The only exception is a story that was moved forward from the last sprint, whose state is “In Progress” and can be declared as done.

    The question now is how do I change the state of the other stories to “In Progress”?

    Thanks again,

    Brian

    #10950

    Nicolas Noullet
    Maître des clés

    Brian,

    All the stories of an « in progress » sprint should be at least « In progress », or done. Can you confirm that the sprint is in progress and you have both « In progress » and « Planned » stories in it?

    #10951

    Kagilum
    Maître des clés

    Yes, sprint 2 is “In Progress” but the tasks are “Planned”.

    #10954

    Nicolas Noullet
    Maître des clés

    Brian,

    Just to be sure, you say that « tasks are Planned » but I was asking about the stories ! Can you confirm that stories are « Planned »?

    If so, that is very unusual and that should not happen. If you want to make the other stories be « in progress » then you can browse the release plan, move the stories to the next sprint and then move them back to the « in progress » sprint. Please note that this may unlink some « done » tasks from the moved story so you may need to move them back to the correct row.

    #10955

    Kagilum
    Maître des clés

    Hi Nicolas,

    Right. I meant to say that the stories are « Planned ».

    Thank you for the suggestion. I will try it out.

    Brian